Land Acquisition

LAND ACQUISITION SawraKuddu
Total land required :
a) Private Land: 46.4791 ha
b) Forest land: 53.9043 ha
Land Acquired so far:a) Private Land: 32.2805 ha(69.45%) b) Forest land: 53.21 ha(98.71%)

Land Acquisition Integrated Kashang

Total Land Required:
Private Land :15.00 ha
Forest Land : 16.71 ha
About 80% of total land required has been acquired.

Land Acquisition Sainj

Total Land Required:
Land : 8.770 ha + 6.053 ha for u/gworks
Forest Land : 47.90 ha
For private land, proceedings under section IX are expected to be completed by Sept., 08.
Case for forest land diversion submitted to Pr.CCF.

LAND ACQUISITION ShongTong
Total land requirement:
Private Land 14.0 ha
Forest Land 68.0 ha
Papers for acquisition of private land are under preparation.
Forest land for various components of the project, approach roads, colony area, quarry site, dumping area etc. has been identified. Papers submitted to Forest Department.

LAND ACQUISITION Renuka
Total land requirement:
Already identified
Private Land 727 ha
Forest Land 461 ha
Govt. Land28 ha
Survey for additional land, required for the reservoir due to change in the top Elevation of dam, is being carried out.
Papers for acquisition of private land are under preparation.
Forest land for various components of the project, approach
roads, colony area, quarry site, dumping area etc. has been
identified. Papers are being submitted to Forest Department.